CCWBE Report

Organization:
National Public Housing Museum
Reporting Period:
Sep 2024
Submitted on:
October 6, 2024
Submitted By:
Mark Jaschke

Pre-Development Projects

Project Goals

What proportion of Goal 1 overall is complete at this point?

100%

What are the barriers and opportunities for completion that impacted goal 1 in the last month?

The CSC Team is actively executing the plan developed in August 2024 to deliver the milestones from the former Project Manager and we are making headway. We are still exploring options for staffing the Retail Store and have brainstormed a model that would engage the select vendors that are selling their product inside the store and online in working at the store certain days of the month. The plan has not been finalized and is still in the early stages of development as an alternative to a workforce development initiative.

What proportion of Goal 2 overall is complete at this point?

80%

What are the barriers and opportunities for completion that you impacted goal 2 in the last month?

The onsite visit that was planned for September 2024 will likely take place in October. We will have an update on that in the October 2024 report filed in November 2024.

What proportion of Goal 3 overall is complete at this point?

30%

What are the barriers and opportunities for completion that you impacted goal 3 in the last month?

A Special Vendor Agreement between CSC and NPHM has been successfully executed at a pop-up event at a local high school and the CSC Team is very pleased with the results of this collaboration. An additional event is planned for October 2024 at the NPHM Building and a new Special Vendor Agreement will be executed just for that event. We expect to report on that in November 2024.

CWB Ecosystem

Did you access Technical Assistance for your CWB project last month?

No

Which TA provider(s) did you work with within the Phase I CWEB grantees?

Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?

Did someone from your organization attend the Working Group this month?

Yes

How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)

Somewhat useful

How would you rate the usefulness of the Working Group for building community?

Somewhat useful

What have been the two most valuable contributions of the Working Group this month?

Collaboration
Community Building

Please share any comments about the working group meetings.

How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)

0

How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)

0

Community Engagement

Number of stakeholder meetings held related to your Pre-Development Project?

4

Number of community meetings attended last month related to your Pre-Development Project?

0

Organizational Capacity

Service / Capacity

Service Capacity

Accounting & Financial Management

4

Advocacy

4

Conflict Resolution

4

Cooperative Development and Operations

4

Education & Training

4

Fundraising or Raising Capital

3 some ability

Governance / Legal

4

Marketing & Communications

4

Other

N/A

Project Management

4

Real Estate Acquisition & Development

5 extensive ability

Relationship Building

5 extensive ability

Research

3 some ability

Other (please describe and include ranking)

What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?

A new bank account and City of Chicago Business License will be applied for in October 2024. The CSC Team is debating the cost of maintaining it’s expired membership with 1871 after the scholarship runs out. .

What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?

The CSC Team was selected to be a part of the new Early Warning Network that was also a CWB Grant recipient.

Optional Space

Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: