What proportion of Goal 1 overall is complete at this point?
100%
What are the barriers and opportunities for completion that impacted goal 1 in the last month?
N/A - we completed in a previous month
What proportion of Goal 2 overall is complete at this point?
100%
What are the barriers and opportunities for completion that you impacted goal 2 in the last month?
N/A - we completed in a previous month
What proportion of Goal 3 overall is complete at this point?
100%
What are the barriers and opportunities for completion that you impacted goal 3 in the last month?
N/A - we completed in a previous month
Did you access Technical Assistance for your CWB project last month?
Yes
Have you worked with TA Provider within the Phase I CWEB grantees or outside the Phase I CWEB grantees or Both?
Both
Which TA provider(s) did you work with within the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Upsidedown Consulting |
15 |
Very satisfied |
Chicago Community Loan Fund |
2 |
Very satisfied |
Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
UChicago Transactional Housing Clinic |
1 |
Very satisfied |
Did someone from your organization attend the Working Group this month?
Yes
How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)
Very useful
How would you rate the usefulness of the Working Group for building community?
Very useful
What have been the two most valuable contributions of the Working Group this month?
Please share any comments about the working group meetings.
How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)
0
How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)
0
Number of stakeholder meetings held related to your Pre-Development Project?
0
Number of community meetings attended last month related to your Pre-Development Project?
0
Service / Capacity
Service | Capacity |
---|---|
Accounting & Financial Management |
4 |
Advocacy |
2 |
Conflict Resolution |
4 |
Cooperative Development and Operations |
5 extensive ability |
Education & Training |
3 some ability |
Fundraising or Raising Capital |
4 |
Governance / Legal |
4 |
Marketing & Communications |
3 some ability |
Other |
N/A |
Project Management |
4 |
Real Estate Acquisition & Development |
4 |
Relationship Building |
5 extensive ability |
Research |
3 some ability |
Other (please describe and include ranking)
What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?
This has been a very busy month, but everything is going well!
What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?
We have been looking at new real estate opportunities and are likely to go under contract for our second building in October! We had a great retreat with our partners at ChiFresh Kitchen and Upside Down Consulting over labor day weekend as well.We also had a great time sharing our story at the USFWC conference. The room was packed and we received great feedback on our model and future plans.
Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: