What proportion of Goal 1 overall is complete at this point?
80%
What are the barriers and opportunities for completion that impacted goal 1 in the last month?
At this point we needed to reevaluate the financial modelo of our project. We also need to complete the finalize the governance and legal structure
What proportion of Goal 2 overall is complete at this point?
20%
What are the barriers and opportunities for completion that you impacted goal 2 in the last month?
We have not have site control of properties at this point
What proportion of Goal 3 overall is complete at this point?
0%
What are the barriers and opportunities for completion that you impacted goal 3 in the last month?
We have not secured site control at this point
Did you access Technical Assistance for your CWB project last month?
No
Which TA provider(s) did you work with within the Phase I CWEB grantees?
Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?
Did someone from your organization attend the Working Group this month?
Yes
How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)
Very useful
How would you rate the usefulness of the Working Group for building community?
Very useful
What have been the two most valuable contributions of the Working Group this month?
Please share any comments about the working group meetings.
The brainstorming sessions have been very helpful
How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)
0
How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)
0
Number of stakeholder meetings held related to your Pre-Development Project?
0
Number of community meetings attended last month related to your Pre-Development Project?
0
Service / Capacity
Service | Capacity |
---|---|
Accounting & Financial Management |
3 some ability |
Advocacy |
3 some ability |
Conflict Resolution |
3 some ability |
Cooperative Development and Operations |
3 some ability |
Education & Training |
3 some ability |
Fundraising or Raising Capital |
3 some ability |
Governance / Legal |
3 some ability |
Marketing & Communications |
3 some ability |
Other |
N/A |
Project Management |
3 some ability |
Real Estate Acquisition & Development |
3 some ability |
Relationship Building |
3 some ability |
Research |
1 limited ability |
Other (please describe and include ranking)
What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?
Limitations were related to delays on information from Consultants
What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?
Support from Consultants that allowed us to continue research
Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: