CCWBE Report

Organization:
Near NorthWest Arts Council
Reporting Period:
Sep 2024
Submitted on:
December 3, 2024
Submitted By:
Kiela Smith

Pre-Development Projects

Project Goals

What proportion of Goal 1 overall is complete at this point?

70%

What are the barriers and opportunities for completion that impacted goal 1 in the last month?

Coop workshop dates scheduled + confirmed with venue; Member selection & Shareholder commitment dependent on completion of architect services; Limitations related to contracting for ADA services (ASL, etc) & confirmed relationship with Accessibility orgs to formalize Advisory council.

What proportion of Goal 2 overall is complete at this point?

80%

What are the barriers and opportunities for completion that you impacted goal 2 in the last month?

Site selection progress; ADA continued planning + implementing in phases with consultant; Began meeting with contracted Financial consultant;

What proportion of Goal 3 overall is complete at this point?

70%

What are the barriers and opportunities for completion that you impacted goal 3 in the last month?

Updated version and training version of slide deck; Scope of work drafts for additional consultants;

CWB Ecosystem

Did you access Technical Assistance for your CWB project last month?

Yes

Which TA provider(s) did you work with within the Phase I CWEB grantees?

TA Provider Hours Spent Satisfaction

Urban Homesteading Assistance Board (UHAB)

2

Very satisfied

Center for Urban Economic Development (CUED)

3

Very satisfied

UIC Law - Community Enterprise & Solidarity Economy Clinic (CESEC)

1

Very satisfied

Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?

TA Provider Hours Spent Satisfaction

Bryan Esenberg

1

Very satisfied

Did someone from your organization attend the Working Group this month?

Yes

How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)

Very useful

How would you rate the usefulness of the Working Group for building community?

Very useful

What have been the two most valuable contributions of the Working Group this month?

Community Building
Knowledge

Please share any comments about the working group meetings.

Grateful for these meetings!

How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)

0

How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)

-2

Community Engagement

Number of stakeholder meetings held related to your Pre-Development Project?

0

Number of community meetings attended last month related to your Pre-Development Project?

7

Organizational Capacity

Service / Capacity

Service Capacity

Accounting & Financial Management

4

Advocacy

4

Conflict Resolution

3 some ability

Cooperative Development and Operations

3 some ability

Education & Training

5 extensive ability

Fundraising or Raising Capital

4

Governance / Legal

3 some ability

Marketing & Communications

3 some ability

Other

N/A

Project Management

3 some ability

Real Estate Acquisition & Development

4

Relationship Building

5 extensive ability

Research

4

Other (please describe and include ranking)

What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?

Continued staff family caregiving adjustments for elder parents with dementia & unexpected emergency

What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?

Research for continued staff and community engagement funding & LOI sent for additional predevelopment funding; Draft of additional digital and physical marketing tools; Development partner research; Funded opportunity to create artwork focused on cooperatives & Cooperatives Bingo game for community engagement;

Optional Space

Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report:

No clear reply from DPD re: grant time extension request through Q1 2025.