What proportion of Goal 1 overall is complete at this point?
50%
What are the barriers and opportunities for completion that impacted goal 1 in the last month?
The goal of engaging community and regularly convening the Advisory Group is on track.
What proportion of Goal 2 overall is complete at this point?
40%
What are the barriers and opportunities for completion that you impacted goal 2 in the last month?
UIC Law provided the group with draft by-laws
What proportion of Goal 3 overall is complete at this point?
50%
What are the barriers and opportunities for completion that you impacted goal 3 in the last month?
This month the group met with Openlands, which is potentially open to providing in kind support with land acquisition.
Did you access Technical Assistance for your CWB project last month?
Yes
Which TA provider(s) did you work with within the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Chicago Community Loan Fund |
1.5 |
Very satisfied |
UIC Law - Community Enterprise & Solidarity Economy Clinic (CESEC) |
5 |
Very satisfied |
Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Chicago Housing Trust |
4 |
Very satisfied |
Trust for Public Land |
3 |
Very satisfied |
Did someone from your organization attend the Working Group this month?
Yes
How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)
Very useful
How would you rate the usefulness of the Working Group for building community?
Very useful
What have been the two most valuable contributions of the Working Group this month?
Please share any comments about the working group meetings.
How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)
0
How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)
0
Number of stakeholder meetings held related to your Pre-Development Project?
4
Number of community meetings attended last month related to your Pre-Development Project?
4
Service / Capacity
Service | Capacity |
---|---|
Accounting & Financial Management |
3 some ability |
Advocacy |
3 some ability |
Conflict Resolution |
3 some ability |
Cooperative Development and Operations |
3 some ability |
Education & Training |
3 some ability |
Fundraising or Raising Capital |
3 some ability |
Governance / Legal |
3 some ability |
Marketing & Communications |
2 |
Other |
N/A |
Project Management |
3 some ability |
Real Estate Acquisition & Development |
2 |
Relationship Building |
4 |
Research |
3 some ability |
Other (please describe and include ranking)
What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?
Community members continue to develop capacity to lead the community land trust.
What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?
The group continues to meet with land owners about potential acquisitions.
Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: