What proportion of Goal 1 overall is complete at this point?
90%
What are the barriers and opportunities for completion that impacted goal 1 in the last month?
Increasing marketing for increased bookings
What proportion of Goal 2 overall is complete at this point?
90%
What are the barriers and opportunities for completion that you impacted goal 2 in the last month?
Re-contracting workers for re-commitment to work
What proportion of Goal 3 overall is complete at this point?
90%
What are the barriers and opportunities for completion that you impacted goal 3 in the last month?
Scheduling time to wrap up contacted work
Did you access Technical Assistance for your CWB project last month?
Yes
Which TA provider(s) did you work with within the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Center for Urban Economic Development (CUED) |
2 |
Very satisfied |
Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Uptima |
3 |
Very satisfied |
Did someone from your organization attend the Working Group this month?
No
How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)
How would you rate the usefulness of the Working Group for building community?
What have been the two most valuable contributions of the Working Group this month?
Please share any comments about the working group meetings.
How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)
0
How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)
1
Number of stakeholder meetings held related to your Pre-Development Project?
2
Number of community meetings attended last month related to your Pre-Development Project?
10
Service / Capacity
Service | Capacity |
---|---|
Accounting & Financial Management |
5 extensive ability |
Advocacy |
3 some ability |
Conflict Resolution |
5 extensive ability |
Cooperative Development and Operations |
5 extensive ability |
Education & Training |
3 some ability |
Fundraising or Raising Capital |
3 some ability |
Governance / Legal |
5 extensive ability |
Marketing & Communications |
5 extensive ability |
Other |
N/A |
Project Management |
5 extensive ability |
Real Estate Acquisition & Development |
N/A |
Relationship Building |
4 |
Research |
2 |
Other (please describe and include ranking)
What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?
Internal capacity has improved this month to finish our contract strong.
What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?
We met with Guidehouse to discuss unapproved expenses and worked to find solutions for spending the remainder of our funding.
Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: