What proportion of Goal 1 overall is complete at this point?
50%
What are the barriers and opportunities for completion that impacted goal 1 in the last month?
ADA digital accessibility vendor initial contact & necessary disability etiquette timelines; Attendance at 4 day UHAB T4T training in NYC to inform future owner training;
What proportion of Goal 2 overall is complete at this point?
50%
What are the barriers and opportunities for completion that you impacted goal 2 in the last month?
Progress on Feasibility study Slide deck updates. Completed stakeholder analysis, market analysis, building types, community analysis and environmental survey for Feasibility study. Preliminary meeting with Prim Lawrence re: Financial analysis.
What proportion of Goal 3 overall is complete at this point?
50%
What are the barriers and opportunities for completion that you impacted goal 3 in the last month?
Regular staff meetings 2x's weekly toward milestone goals. Strategic planning content usage. Identification of possible vendors for future architectural and accounting needs. Limited funds for initial vendor retainers.
Did you access Technical Assistance for your CWB project last month?
Yes
Have you worked with TA Provider within the Phase I CWEB grantees or outside the Phase I CWEB grantees or Both?
Both
Which TA provider(s) did you work with within the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Urban Homesteading Assistance Board (UHAB) |
30 |
Very satisfied |
Center for Urban Economic Development (CUED) |
2 |
Very satisfied |
Which TA providers did you work with OUTSIDE of the Phase I CWEB grantees?
TA Provider | Hours Spent | Satisfaction |
---|---|---|
Polsky center |
2 |
Very satisfied |
World Business Chicago |
1 |
Somewhat satisfied |
Did someone from your organization attend the Working Group this month?
No
How would you rate the usefulness of the working group to your project last month? (on a scale of 1-5)
Very useful
How would you rate the usefulness of the Working Group for building community?
Very useful
What have been the two most valuable contributions of the Working Group this month?
Please share any comments about the working group meetings.
How many TOTAL housing units did you preserve or create last month? (it is okay if the answer is zero)
0
How many TOTAL CWB businesses did you develop last month? (it is okay if the answer is zero)
0
Number of stakeholder meetings held related to your Pre-Development Project?
1
Number of community meetings attended last month related to your Pre-Development Project?
2
Service / Capacity
Service | Capacity |
---|---|
Accounting & Financial Management |
4 |
Advocacy |
4 |
Conflict Resolution |
3 some ability |
Cooperative Development and Operations |
3 some ability |
Education & Training |
5 extensive ability |
Fundraising or Raising Capital |
4 |
Governance / Legal |
3 some ability |
Marketing & Communications |
3 some ability |
Other |
N/A |
Project Management |
3 some ability |
Real Estate Acquisition & Development |
4 |
Relationship Building |
5 extensive ability |
Research |
4 |
Other (please describe and include ranking)
What constraints or limitations with internal capacity is the organizarion experiencing related to its Pre-Development Project?
balancing cash flow to facilitate continued work; family caregiving needs; speed of partnership progression
What opportunities, if any, did the organization take advantage of related to its Pre-Development Project?
Enhanced ETOD project and Climate action funding awareness.
Please use this space to elaborate, contextualize, or add any additional info about the details submitted in your report: